A subcontractor is responsible for outfitting six satellites that will be used for solar research. Four of

Question:

A subcontractor is responsible for outfitting six satellites that will be used for solar research. Four of the six have been completed in a total of 600 hours. If the crew has a 75 percent learning curve, how long should it take them to finish the last two units?