A worker-machine operation was found to involve 3.3 minutes of machine time per cycle. In the course

Question:

A worker-machine operation was found to involve 3.3 minutes of machine time per cycle. In the course of 40 cycles of a stopwatch time study, the worker’s time loading and unloading the machine averaged 1.9 minutes per cycle, and the worker was given a rating of 120 percent. Assuming an allowance factor of 12 percent of job time, determine the standard time for this job (including the machine time).