An assembly line with 16 tasks needs to be balanced. The line operates 7 hours a day,

Question:

An assembly line with 16 tasks needs to be balanced. The line operates 7 hours a day, and the desired daily output rate is 70 units. The total time for all the 16 tasks is 38 minutes:

1. What is the cycle time?

2. What is the theoretical minimum number of workstations required?

3. What cycle time will provide a daily output rate of 105 units?