An autoglass company located in Detroit produces mirrors for automobiles. The company supplies auto mirrors to a
Question:
An autoglass company located in Detroit produces mirrors for automobiles. The company supplies auto mirrors to a nearby Ford (The Ford Motor Company, Dearborn, MI) plant. The demand for mirrors from the Ford plant is 800 mirrors per day. The autoglass company’s productive time is 480 minutes:
1. What is the takt time?
2. If the total standard operating time required to produce a mirror is 144 seconds, how many workers are needed?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management Managing Global Supply Chains
ISBN: 978-1506302935
1st edition
Authors: Ray R. Venkataraman, Jeffrey K. Pinto
Question Posted: