As part of a major plant renovation project, the industrial engineering department has been asked to balance

Question:

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output rate of240 units per eight- hour day. Task times and precedence relationships are as follows:

image text in transcribed
Do each of the following:
a. Draw the precedence network.
b. Determine tire required cycle time.
c. Determine the minimum number of workstations needed.
d. Assign the tasks to workstations using the heuristic rule “Assign the task with the most followers.” Use the heuristic rule “Assign the task with the longest time” as a tiebreaker, If a tie still exists, choose randomly,
e. Calculate the percentage idle time for the assignments in part d.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: