Bob Carlton's golf camp estimates the following staff requirements for its services over the next 2 years.

Question:

Bob Carlton's golf camp estimates the following staff requirements for its services over the next 2 years.Quarter Demand (hours) Quarter Demand (hours) 1 4,200 5 4,400 2 3 6,400 3,000 6 7 6,240 3,600 4 4,800 8 4,800

regular time and can work an additional 120 hours overtime. Regular-time wages and benefits cost Carlton $7,200 per employee per quarter for regular time worked up to 480 hours, with an overtime cost of $20 per hour. Unused regular time for certified instructors is paid at $15 per hour. There is no cost for unused overtime capacity. The cost of hiring, training, and certifying a new employee is $10,000. Layoff costs are $4,000 per employee. Currently, eight employees work in this capacity.
a. Find a staffing plan using the level strategy that allows for no delay in service. It should rely only on overtime and the minimum amount of undertime necessary. What is the total cost of this plan?
b. Use a chase strategy that varies the workforce level without using overtime or undertime. What is the total cost of this plan?
c. Propose a better plan and calculate its total cost.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Processes And Supply Chains

ISBN: 9781292409863

13th Global Edition

Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman

Question Posted: