Component K has the following weekly demand requirements: The ordering cost for this item is $100/order and
Question:
The ordering cost for this item is $100/order and holding cost is $1/unit/week (in U.S. dollars). To develop a material requirements plan for this component, which of the following lot-sizing techniques will yield the lowest total cost?
1. EOQ.
2. 2-week fixed-period ordering.
3. Lot-for-lot.
4. Part-period balancing (PPB).