Draw a Gantt chart and find the value of make-span (time to complete all jobs) using the
Question:
Draw a Gantt chart and find the value of make-span (time to complete all jobs) using the sequence A–B–C–D–E for the following problem:
Processing Time (Days)
Job M1 M2 A 8 6 B 9 4 C 3 7 D 2 6 E 6 5 Use the data given in the following table to answer the next four problems. The table gives the order in which five jobs arrived in the production department; their processing times and due dates.
Job Processing Time (Days) Due Date (Days)
A 18 46 B 13 33 C 21 25 D 19 52 E 24 48