Estimate the time it will take to complete the fourth unit of a 12-unit job involving a

Question:

Estimate the time it will take to complete the fourth unit of a 12-unit job involving a large assembly if the initial unit required approximately 80 hours for each of these learning percentages:
a. 72 percent
b. 87 percent
c. 95 percent