For the set of tasks given below, do the following: a. Develop the precedence diagram. b. Determine

Question:

For the set of tasks given below, do the following:

image text in transcribed


a. Develop the precedence diagram.

b. Determine the minimum cycle time and then calculate the cycle time for a desired output of 500 units in a seven-hour day. Why might a manager use a cycle time of 50 seconds?

c. Determine the minimum number of workstations for output of 500 units per day.

d. Balance the line using the greatest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.

e. Calculate the percentage idle time for theline.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0078024108

12th edition

Authors: William J Stevenson

Question Posted: