he times required to complete each of five jobs in a two-machine flow strop are shown in
Question:
he times required to complete each of five jobs in a two-machine flow strop are shown in the following table. Each job must follow the same sequence, begin with machine A and end with machine B.
a. Determine a sequence that will minimize the make-span.
b. Construct a load/schedule Gantt chart for the resulting sequence, and find machine B’s idle time.
c. For the sequence determined in part a, can machine B’s idle time be reduced by splitting some jobs in half? If so, which jobs? Draw the new load'1 schedule Gantt chart.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 978-0071091428
4th Canadian edition
Authors: William J Stevenson, Mehran Hojati
Question Posted: