Question: NewApp Software Production (see Problem 12) estimates that it takes a full year for each developer to produce one app. However, after a recent process

NewApp Software Production (see Problem 12) estimates that it takes a full year for each developer to produce one app. However, after a recent process audit, it was discovered that each developer, on average, spends only 25 hours a week directly working on the app.

Assume developers work 9 hours per day, 5 days per week, 48 weeks per year. What is the process velocity?