Suppose the length of critical path in a project is 50 days and the standard deviation is
Question:
Suppose the length of critical path in a project is 50 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing the project is 90%? Round the answer to the nearest higher integer.