Suppose the length of critical path in a project is 40 days. There are four activities A,

Question:

Suppose the length of critical path in a project is 40 days. There are four activities A, B, C, and D on the critical path. The variances of these activities are: A (1.4), B (1.2), C (0.9), and D (0.4). What is the probability of completing the project within 42 days?