Suppose you have three jobs waiting to be completed, and you must determine the sequence in which

Question:

Suppose you have three jobs waiting to be completed, and you must determine the sequence in which these jobs should be worked on. You calculated the critical ratio for each of the jobs and the results were that job A has a critical ratio of 1.27, job B has a critical ratio of -0.89, and job C has a critical ratio of 0.15. Which of these jobs is not late at this moment, but will be late?