Task C has two immediate predecessors, tasks A and B. Task A has an early finish time

Question:

Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of 3 days, and task B has an early finish time of 5 days. Task C is 2 days long. What is the early finish time of task C?