The following precedence network displays the 3-Point estimates for each activity of a project. Determine: a. The

Question:

The following precedence network displays the 3-Point estimates for each activity of a project. Determine:
a. The expected duration for each path and its variance.
b. The probability that the project will require more than 49 weeks.
c. The probability that the project can be completed in 46 weeks or less.

image text in transcribed
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: