The following table shows the probabilistic activity time estimates for the CPM/PERT network in Problem 9-9. Determine

Question:

The following table shows the probabilistic activity time estimates for the CPM/PERT network in Problem 9-9.


Time Estimates (days) Activity a m 1 1 3 5 10 4 6. 14 4 9. 6. 3 7 1 1.5 1 1 1 10 2 4 11 12 2. 3. 2. 2. 3.


Determine the following:
a. Expected activity times
b. Earliest start and finish times
c. Latest start and finish times
d. Activity slack
e. Critical path
f. Expected project duration and standard deviation


Problem 9-9

In one of the little-known battles of the U.S. Civil War, General Tecumseh Beauregard lost the Third Battle of Bull Run because his preparations were not complete when the enemy attacked. If the critical path method had been avail-able, the general could have planned better. Suppose that the following project network with activity times in days had been available. 


Move Build Create engineering division pontoon bridges supply lines 2 5 11 2 2 Advance cavalry Develop plan Artillery Ca

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Creating Value Along the Supply Chain

ISBN: 978-1118301173

1st Canadian Edition

Authors: Roberta S. Russell, Bernard W. Taylor, Ignacio Castillo, Navneet Vidyarthi

Question Posted: