The following table shows the probabilistic activity time estimates for the CPM/PERT network in Problem 9-9. Determine
Question:
Determine the following:
a. Expected activity times
b. Earliest start and finish times
c. Latest start and finish times
d. Activity slack
e. Critical path
f. Expected project duration and standard deviation
Problem 9-9
In one of the little-known battles of the U.S. Civil War, General Tecumseh Beauregard lost the Third Battle of Bull Run because his preparations were not complete when the enemy attacked. If the critical path method had been avail-able, the general could have planned better. Suppose that the following project network with activity times in days had been available.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management Creating Value Along the Supply Chain
ISBN: 978-1118301173
1st Canadian Edition
Authors: Roberta S. Russell, Bernard W. Taylor, Ignacio Castillo, Navneet Vidyarthi
Question Posted: