Using PERT, Jennifer Benson was able to determine that the expected project completion time for the construction

Question:

Using PERT, Jennifer Benson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4.
a) What is the probability that the project will be completed in 17 months?
b) What is the probability that the project will be completed in 20 months?
c) What is the probability that the project will be completed in 23 months?
d) What is the probability that the project will be completed in25 months? 
e) What is the due date that yields a 95% chance of completion?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Sustainability and Supply Chain Management

ISBN: 978-0133764345

2nd Canadian edition

Authors: Jay Heizer, Barry Render, Paul Griffin

Question Posted: