What is the minimum cost of crashing by four days the following project that James Walters manages

Question:

What is the minimum cost of crashing by four days the following project that James Walters manages at Athabasca University?

Normal Crash Time Time Normal Crash Immediate Activity (days) (days) Cost Cost Predecessor(s) $ 900 $1000 A 5 B 8. 300 4