Thabo Mbeki, president of Mbeki Construction, has developed the tasks, durations, and predecessor relationships in the following

Question:

Thabo Mbeki, president of Mbeki Construction, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.

Time Estimates (in weeks) Immediate Most Activity Predecessor(s) Optimistic Likely Pessimistic 4 10 B A 2 8 24 A 8 12 16


a) What is the expected (estimated) time for activity C?
b) What is the variance for activity C?
c) Based on the calculation of estimated times, what is the critical path?
d) What is the estimated time of the critical path?
e) What is the activity variance along the critical path?
f) What is the probability of completion of the project before week 36?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Sustainability and Supply Chain Management

ISBN: 978-0133764345

2nd Canadian edition

Authors: Jay Heizer, Barry Render, Paul Griffin

Question Posted: