Using the given information, calculate the gross requirements for each of the components when the company plans

Question:

Using the given information, calculate the gross requirements for each of the components when the company plans to build 80 of its Q Models if you have these inventories: 80 units of component T and 200 units of component R.

Item Q R S T X Y V Z Usage per Parent  2 1 3 2 1 2 Load Time (weeks) 2 4 3 2 2 3 3 4