Using the information presented in the following table, identify' the processing sequence that would result using (1)
Question:
Using the information presented in the following table, identify' the processing sequence that would result using (1) MST, (2) SPT, (3) EDD, and (4) CR. For each priority rule, determine (I) average flow time, (2) average hours late, and (3) average W1P. Is one priority rule superior to the others? Explain. (Hint: First determine the total job time for each job by calculating the total processing time for the job and then adding in the setup time. All rimes are in hours.)