Using the job information in Problem 3, Construct a Gantt chart using the critical ratio (CR) rule
Question:
Using the job information in Problem 3, Construct a Gantt chart using the critical ratio (CR) rule to determine the job priority ranking. Assume all jobs arrived simultaneously. Determine the makespan , average flowtime , average queue time, average lateness, and average tardiness. Also assume that transfer times are zero. Which rule performed better, the EDD rule from Problem 3, or the CR rule? Explain.