Using the job information in Problem 3, Construct a Gantt chart using the critical ratio (CR) rule

Question:

Using the job information in Problem 3, Construct a Gantt chart using the critical ratio (CR) rule to determine the job priority ranking. Assume all jobs arrived simultaneously. Determine the makespan , average flowtime , average queue time, average lateness, and average tardiness. Also assume that transfer times are zero. Which rule performed better, the EDD rule from Problem 3, or the CR rule? Explain.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: