What is the definition of the latest completion time (LCT) of a project activity? a. LCT(A i
Question:
What is the definition of the latest completion time (LCT) of a project activity?
a. LCT(Ai) = Max{LST(Aj) for which Aj is a successor of Ai}
b. LCT(Ai) = Min{LST(Aj) for which Aj is a successor of Ai}
c. LCT(Ai) = Max{LST(Aj) for which Aj is a predecessor of Ai}
d. LCT(Ai) = Min{LST(Aj) for which Aj is a predecessor of Ai}