Which applies when using the critical ratio (CR) to schedule work? a) A CR of more than
Question:
Which applies when using the critical ratio (CR) to schedule work?
a) A CR of more than 1.0 means that the job has some slack.
b) A job with a CR of 1.0 should be given highest priority.
c) A job with a CR of 2.0 should be scheduled first.
d) We first schedule the job with the highest CR.