Which of the following is not included in an activity-on-node diagram: (a) the critical activities (b) the

Question:

Which of the following is not included in an activity-on-node diagram:

(a) the critical activities

(b) the float

(c) the activity number or description

(d) the earliest start time

(e) the latest finish time.