11 A bank is trying to determine which of two machines should be rented to process checks....
Question:
11 A bank is trying to determine which of two machines should be rented to process checks. Machine 1 rents for
$10,000 per year and processes 1,000 checks per hour.
Machine 2 rents for $15,000 per year and processes 1,600 checks per hour. Assume that the machines work 8 hours a day, 5 days a week, 50 weeks a year. The bank must process an average of 800 checks per hour, and the average check processed is for $100. Assume an annual interest rate of 20%. Then determine the cost to the bank (in lost interest)
for each hour that a check spends waiting for and undergoing processing. Assuming that interarrival times and service times are exponential, which machine should the bank rent?