19. ln an effort to identify stakeholders who may be .iffected by your project, you're looking over...

Question:

19. ln an effort to identify stakeholders who may be .iffected by your project, you're looking over the organiutional structure of your client's company. As you identify stakeholders on the organizational cha.rt, you request meetings with each stakeholder. You'll document the information you learn about each stakeholder i11 the stakeholder register. 111is register can then be used as an input to which of the following processes?

A. Pl.in Risk M.magcment and Collect Requirements B. Perform h1tegrat<'d Change Control :md Plan Commun11:ations Ma11.1gcment C. Pl,m ~i.1lity Management and Manage Quality D. ldcntify Ri3b and Develop Proiect Charter

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: