27. Your project has just been fast tracked, and you arc looking to quickly bring in a...
Question:
27. Your project has just been fast tracked, and you arc looking to quickly bring in a subcontractor to complet<• networking. There is no time to issue a request for proposal (RFP), so you choose to use a company you have uscJ many times before for software development. A primacy concern in this
;ituation 1;:
A. Collusion between subcontractors <..
B. "The subcontractor's qu.ilifications C. The subcontractor's evaluation criteria/
D. Holding a bidder conference '<