27. Your project has just been fast tracked, and you arc looking to quickly bring in a...

Question:

27. Your project has just been fast tracked, and you arc looking to quickly bring in a subcontractor to complet<• networking. There is no time to issue a request for proposal (RFP), so you choose to use a company you have uscJ many times before for software development. A primacy concern in this

;ituation 1;:

A. Collusion between subcontractors <..

B. "The subcontractor's qu.ilifications C. The subcontractor's evaluation criteria/

D. Holding a bidder conference '<