29. After much hard work, the procurement statement of work for the project is completed. However, even

Question:

29. After much hard work, the procurement statement of work for the project is completed. However, even alter g.un1ng agreement that the procurement statement of work is complete, the project manager is unsure of whether it actually addresses .111 the buyer's ne(~ds. The project man.1ger is .1bout to attend the bidder conferer11.:e. Ht• asks you for advice on what to do during the session. Which of the following is the best advice you can give him?

A. You do not need to attend this session; the procurement manager will hold it. "'-

B. Make sure you negotiate project scope.

C. Make sure you give all the sdlers the opportunity to ask questions.

D. Let the project sponsor handle the meeting so you can be the good guy in the negotiation session.-<-