33. 1be project team is considering the prospective sellers who have submitted proposals. One team member supports

Question:

33. 1be project team is considering the prospective sellers who have submitted proposals. One team member supports a certain seller while another team member wants the project to be awarded to a different seller. 'TI1c project manager should remind the team that the best thing to focus on in order to m,\kc a selection is the:

A. Procurement documents B. Procurement audits C. Source selection criteria D. Procurement management plan