35. ; project manager 1s creating a risk response plan. However, every time a ri~k response is...

Question:

35. ;\ project manager 1s creating a risk response plan. However, every time a ri~k response is suggested,

.mother risk is identified that is caused by the response. Which of the following is the best thing for the project manager to do?

A. Get more people involved in the Identify Risks process, since risks have been missed.

B. Make sure the project work is better understood.

C. Spend more time makmg sure the nsk responses are dearly defined.

D. Document the new risks and continu<' the Pl.ui Risk Responses process.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: