36. Your organizatton has recently been informed that sever.11 of the regulations related to how your products

Question:

36. Your organizatton has recently been informed that sever.11 of the regulations related to how your products are manufactured will change in six months. ln planning for work to change certain design and production processes, you determine you will need to work with 5evera1 external organizations to do the work. Which type of contract do you not want to use if you do not ha\'C enough help to audit invoices?

A. Cost plus fixed fee (CPFF)

B. Time & material (T&M)

C. Fixed-price (FP)

D. Fixed price incentive fee (FPIF)