Question:

y' 4. A project m.rnager for the seller is told by her management that the project team should do whatever possible to be awarded incentive money. TI1e primary objective of incentive clauses in a contnct is to:

A. Reduce costs for the buyer.

B. Help the seller control costs.

C. Synchronize objectives.

D. Reduce risk for the seller by shifting risk to the buyer.