In Example 11.3, we commented on the 95th percentile on days required in cell I35 and the

Question:

In Example 11.3, we commented on the 95th percentile on days required in cell I35 and the corresponding date in cell J35. If the company begins production on this date, then it is 95% sure to complete the order by the due date. We found this date to be August