Question: Estimate the group efficiency of a 4 6 pile group, consisting of 400 mm diameter concrete piles at 1.2 m center-tocenter spacing using a.
Estimate the group efficiency of a 4 × 6 pile group, consisting of 400 mm diameter concrete piles at 1.2 m center-tocenter spacing using
a. The converse-labarre equation
b. The los angeles group action equation
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
Given Data Pile group size 4 x 6 Number of pile rows m 4 Number of pile ... View full answer