For a sand drain project (Figure 5.20), the following are given: Clay: Normally consolidated H c =

Question:

For a sand drain project (Figure 5.20), the following are given:

Clay: Normally consolidated

Hc = 5.5 m sone{way drainaged

Cc = 0.3

eo = 0.76

cv = 0.015 m2/day

Effective overburden pressure at the middle of clay layer = 80 kN/m2

Sand drain: rw = 0.07 m

rw = rs

de = 2.5 m

cv = cvr

A surcharge is applied as shown in Figure P5.13. Calculate the degree of consolidation and the consolidation settlement 50 days after the beginning of the surcharge application.


Figure 5.20

Surcharge Groundwater table Sand Vertical drainage Sand drain Sand drain radius = rw Radial drainage He Radial drainage Clay layer Vertical drainage Sand (a) Section Sand drain radius = rw de (b) Plan


Figure P5.13.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Principles Of Foundation Engineering

ISBN: 9781337705028

9th Edition

Authors: Braja M. Das, Nagaratnam Sivakugan

Question Posted: