Question: Refer to Figure 18.13. Given L 1 = 1.5 m, L 2 = 3 m; for the sand, ' = 33, = 16.5 kN/m
Refer to Figure 18.13. Given L1 = 1.5 m, L2 = 3 m; for the sand, ϕ' = 33°, γ = 16.5 kN/m3, γsat = 19.0 kN/m3; and, for the clay, c = 50 kN/m2, ϕ = 0, and γsat = 20 kN/m3. Determine the depth of sheet pile required, allowing for a 50% increase from the theoretical estimate.
Figure 18.13.

Sand L1 Water C = 0 table Sand Ysat C = 0 L2 P1 Dredge line F E o'2 D 06 L3 Clay Ysat G 0 = 0 H B
Step by Step Solution
3.34 Rating (160 Votes )
There are 3 Steps involved in it
To determine the depth of sheet pile required we can use the following steps Calculate the active earth pressure at the top of the clay layer Calculat... View full answer