Bobcat uses a traditional cost system and estimates next years overhead will be $800,000, as driven by

Question:

Bobcat uses a traditional cost system and estimates next year’s overhead will be $800,000, as driven by the estimated 25,000 direct labor hours. It manufactures three products and estimates the following costs:image

If the labor rate is $30 per hour, what is the per-unit cost of each product?