An end item has the product structure diagram given in Figure 87. a. Write the product structure

Question:

An end item has the product structure diagram given in Figure 8–7.

a. Write the product structure diagram as an indented bill-of-materials list.

b. Suppose that the MPS for the end item is Week 30 31 32 33 34 35 MPS 165 180 300 220 200 240 If production is scheduled on a lot-for-lot basis, find the planned order release for component F.

c. Using the data in part (b), find the planned order release for component I.

d. Using the data in part (b), find the planned order release for component H.