Planned order releases (POR) for three components, A, B, and C, are given below. Suppose that the
Question:
Planned order releases (POR) for three components, A, B, and C, are given below.
Suppose that the yields for these components are respectively 84 percent, 92 percent, and 70 percent. Assuming lot-for-lot scheduling, how should these planned order releases be adjusted to account for the fact that the yields are less than 100 percent?
Week 6 7 8 9 10 11 12 13 14 15 16 17 POR(A) 200 200 80 80 200 400 400 400 POR(B) 100 100 40 40 100 200 200 200 POR(C) 200 400 280 100 280 600 800 800 400