The time-phased net requirements for the base assembly in a table lamp over the next six weeks

Question:

The time-phased net requirements for the base assembly in a table lamp over the next six weeks are Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week.

a. What lot sizing do you obtain from the EOQ formula?

b. Determine the lot sizes using the Silver–Meal heuristic.

c. Determine the lot sizes using the least unit cost heuristic.

d. Determine the lot sizes using part period balancing.

e. Compare the holding and setup costs obtained over the six periods using the policies found in parts

(a) through

(d) with the cost of a lot-for-lot policy.

Problems 18–22 are based on the material appearing in Appendix 8–A.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Production And Operations Analysis

ISBN: 9781478623069

7th Edition

Authors: Steven Nahmias, Tava Lennon Olsen

Question Posted: