12.47 Metro hypermarket in Kuwait supplies juice boxes from a manufacturer in Saudi Arabia. Daily demand is
Question:
• • 12.47 Metro hypermarket in Kuwait supplies juice boxes from a manufacturer in Saudi Arabia. Daily demand is almost constant at 100 boxes per day. The lead time for boxes delivery is normally distributed with a mean of 5 days and a standard deviation of 2 days. The hypermarket has a 95% service level. Compute Metro’s ROP.