14.16 You have just been notified that the lead time for component G of product A (Problem...
Question:
• • • 14.16 You have just been notified that the lead time for component G of product A (Problem 14.15 and Figure 14.14) has been increased to 5 weeks.
a) Which items have changed, and why?
b) What are the implications for the production plan?
c) As production planner, what can you do?