14.26 M. de Koster, of Rene Enterprises, has the master production plan shown here: Lead time =...

Question:

• • 14.26 M. de Koster, of Rene Enterprises, has the master production plan shown here:

image text in transcribed

Lead time = 1 period; setup cost = $200; holding cost = $10 per week; stockout cost = $10 per week. Your job is to develop an ordering plan and costs for:

a) Lot-for-lot.

b) EOQ.

c) POQ.

d) Which plan has the lowest cost?