14.29 Karl Knapps, Inc., has received the following orders: The entire fabrication for these units is scheduled

Question:

• • • 14.29 Karl Knapps, Inc., has received the following orders:

image text in transcribed

The entire fabrication for these units is scheduled on one machine.
There are 2,250 usable minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan, using lot splitting, for the 10-week time period.