3.9 Task time estimates for the modification of an assembly line at Jim Goodales Carbondale, Illinois, factory

Question:

•• 3.9 Task time estimates for the modification of an assembly line at Jim Goodale’s Carbondale, Illinois, factory are as follows:

image text in transcribed

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project completion time?

d) Draw a Gantt chart for the project.

Step by Step Answer: