4 In a typical 7-day period, the planning department of the pizza company programs its Pizzamatic machine
Question:
4 In a typical 7-day period, the planning department of the pizza company programs its ‘Pizzamatic’
machine for 148 hours. It knows that changeovers and set-ups take 8 hours and breakdowns average 4 hours each week. Waiting for ingredients to be delivered usually accounts for 6 hours, during which the machine cannot work. When the machine is running, it averages 87 per cent of its design speed.
An inspection has revealed that 2 per cent of the pizzas processed by the machine are not up to the company’s quality standard. Calculate the OEE of the ‘Pizzamatic’ machine.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 978-1292408248
10th Edition
Authors: Nigel Slack ,Alistair Brandon-Jones ,Nicola Burgess
Question Posted: