4. The statement the quantity and schedule is always planned to produce the final product over a...
Question:
4. The statement "the quantity and schedule is always planned to produce the final product over a specific time period" is related to:
(a) MRP files
(b) Bill of material (BOM)
(c) Master production schedule (MPS)
(d) Planning time frame